Optimus Gen-3 Program
Reservation window open Gen-3  /  Rev. C  /  Production run 2027

Put a humanoid on the line.

Optimus Gen-3 is a bipedal work platform that picks up your tools, walks your floors and follows your procedures. No retooling. No safety cages. No bespoke end-effectors for every task.

Standing height
1,732mm
Dry mass
68kg
Rated payload
24kg
Shift runtime
9.5h
Head and shoulders of an Optimus Gen-3 humanoid unit, showing the sensor visor and white composite shell. Sensor dome Stereo visor Shoulder yoke
Unit 0042  ·  pre-production
§ 01 — Overview

The floor doesn't change.
The worker does.

Fixed automation asks the building to adapt: new fixtures, new guarding, new line balance, six months of integration. Gen-3 inverts that. It is shaped like the person who did the job yesterday, so it inherits the workspace as it already exists.

See how it is built

Integration time

11 days

Median from crate to first supervised production task across 14 pilot sites.

Task library

340+

Pre-trained manipulation and locomotion behaviours shipped with every unit.

Fleet uptime

97.4%

Rolling 90-day availability across the Gen-2 fleet still in daily service.

Retooling required

Zero

No fixtures, no floor anchors, no line stoppage. It walks in and starts learning.

Designed backwards,
from the task.

Gen-3 started as a list of 212 jobs our pilot customers could not automate. Every joint, every gear ratio and every gram of the chassis was argued against that list — not against a spec sheet.

  • Human-scale reach envelope1,732 mm standing, 512 mm shoulder span — passes any door and aisle a person can.
  • Tool-agnostic handsFive-digit manipulators with tactile pads grip the drill, the tote and the clipboard already on site.
  • Force-limited by constructionSeries-elastic actuation caps contact force in hardware, not just in software policy.
  • Serviceable in the aisleEleven line-replaceable modules. A limb swap is a 6-minute, two-bolt procedure.
Engineer's desk with hand-drawn mechanical schematics, calipers and component sketches for the Gen-3 limb assembly.
§ 02 — Systems

Six subsystems.
One body.

Select a marker on the drawing — or a subsystem below — to read the engineering notes for that assembly. Every figure on this page is drawn from the Rev. C production release.

Technical front elevation of the Optimus Gen-3 humanoid Line drawing showing head and sensor visor, thermal chest vents, power core, arm assemblies, five-digit manipulators, and bipedal leg assemblies, with overall height and shoulder span dimensions. 1 732 MM SPAN 512 MM DATUM · FLOOR PLANE
Assembly 01 / 06

Perception head

Placeholder

    A humanoid unit standing in front of an illuminated test console in a darkened environmental chamber.
    Fig. 2.1 — Rev. C unit under environmental qualification
    § 03 — Capability

    What a shift
    actually looks like.

    Gen-3 ships with a behaviour library, not a demo reel. Everything below runs on the standard unit with no additional hardware.

    01

    Sees clutter, not fixtures

    Stereo depth plus rolling LiDAR builds a fresh scene model every 40 ms, so a pallet left in the wrong place is an obstacle — not a failed run.

    02

    Uses the tools you own

    Five-digit manipulators with 1,100 tactile taxels per palm. Trigger tools, latches, totes and touchscreens — no custom end-effector programme.

    03

    Learns by being shown

    A supervisor walks the unit through a task twice in teach mode. The policy generalises across the cell and syncs to every other unit on site.

    04

    Stops before it touches

    Dual redundant safety controller, capacitive skin on every proximal link and a certified 118 ms stop from full gait.

    05

    Runs the whole shift

    9.5 h nominal duty on a 2.4 kWh pack, or continuous operation with a 90-second hot swap at the dock.

    06

    Thinks on board

    All perception and control run locally. Network loss degrades reporting, never motion safety or task execution.

    Close-up of a white five-digit robotic hand with articulated finger joints.
    Fig. 3.1 — Manipulator, 22 DOF per pair
    § 04 — Deployment

    Where Gen-2
    already works.

    Figures below are measured from live sites running the previous generation. Gen-3 carries the same behaviour library forward with roughly 1.6× the cycle speed.

    Wide view of a distribution warehouse with racked yellow totes stretching into the distance. Case 4.1

    Intralogistics

    Tote induction, mixed-case decanting and cycle counting across aisles that were never designed for an AMR footprint.

    1,240Picks / shift
    0.4%Mis-pick rate
    Automotive body-in-white line with industrial robot arms working on a vehicle shell. Case 4.2

    Line-side supply

    Kitting, fastener replenishment and machine tending on legacy cells where guarding a new arm would have cost more than the arm.

    18 sMean cycle
    3.1×Cells / unit
    Technician in safety goggles closely inspecting work, seen in profile. Case 4.3

    Inspection rounds

    Gauge reading, valve state checks and thermal sweeps on fixed routes through plant rooms, at night, without lighting changes.

    96Points / round
    24/7Route coverage
    § 05 — Specifications

    Rev. C
    datasheet.

    Values are nominal at 20 °C on a level datum with a 24 kg payload. Full mechanical and electrical drawings are released under NDA at reservation stage two.

    Optimus Gen-3 Core — mechanical, power and control values.

    Gen-3 is a general-purpose platform and is not certified for use in explosive atmospheres, in contact with foodstuffs, or as a component of a life-safety system. See the Product Disclaimer.

    § 06 — Safety & autonomy

    Autonomy with
    a hand on the brake.

    Gen-3 is designed for shared floors. Authority is layered so that the fastest loop is always the one that stops the machine, and a person can always take that loop.

    Operations corridor lined with illuminated equipment racks, a supervisor walking between them.
    • Hardware safety layerA dual-channel controller independent of the autonomy stack holds torque limits and the stop circuit. It cannot be overridden by a task policy.
    • Supervisory autonomyUnits execute assigned tasks independently and escalate anything outside the accepted envelope to a human operator instead of improvising.
    • Auditable by defaultEvery motion command, perception frame reference and operator intervention is written to a signed on-board log, retained for 90 days.
    • Local-first dataPerception data is processed on board. Nothing leaves the site unless your administrator enables fleet telemetry — see the Privacy Policy.
    • Signed, staged updatesFirmware is cryptographically signed and rolls out per-cohort with an automatic rollback on any regression in the safety self-test.
    § 07 — Program

    From reservation
    to first shift.

    Reservations are sequenced by build slot, not by order value. You can withdraw at any point before stage four and the deposit is returned in full.

    An engineer working at a production cell, checking an assembly against a terminal.
    Every unit is hand-verified against its build sheet before commissioning.
    Stage 01 — Day 0

    Reserve a slot

    A refundable deposit holds a position in the 2027 build queue. No configuration is locked and nothing is charged beyond the deposit.

    Stage 02 — Week 2

    Technical review

    Our applications team reviews your task list against the behaviour library and returns a written feasibility note, with the full datasheet under NDA.

    Stage 03 — Week 6

    Site survey

    A remote or on-site survey of aisles, floor finish, lighting and network. You receive a readiness report and a fixed integration quote.

    Stage 04 — Delivery

    Commissioning

    Units arrive crated and calibrated. Two days of supervised teach-in, then handover to your own operators with 12 months of included support.

    § 08 — Configurations

    Three builds.
    One platform.

    Every configuration shares the same chassis, safety controller and behaviour library. The differences are actuation class, pack capacity and support tier. Indicative list prices, per unit, excluding duties and local taxes.

    Gen-3 Core

    Single-cell pilots

    $72,000Deposit $2,500 — refundable

    • 24 kg rated payload, 28 DOF
    • 2.4 kWh pack, 9.5 h nominal
    • Standard behaviour library
    • 12 months business-hours support
    Reserve Core
    Most reserved

    Gen-3 Pro

    Multi-shift production

    $104,000Deposit $5,000 — refundable

    • 32 kg payload, high-torque wrists
    • 3.6 kWh hot-swap pack + dock
    • Teach-mode authoring licence
    • Fleet console for up to 25 units
    • 24 months 4-hour response
    Reserve Pro

    Gen-3 Max

    Fleet operations

    $149,000Deposit $7,500 — refundable

    • Everything in Pro
    • Sealed IP54 field chassis
    • On-premise policy training node
    • Named reliability engineer
    Reserve Max
    Build slots — 2027 run

    412 of 1,800 slots remain.

    Slots are allocated in the order reservations are confirmed. Deposits are fully refundable until the site survey is signed off.

    Reserve a unit
    § 09 — Questions

    Asked before
    every pilot.

    If your question is not here, write to [email protected] and an applications engineer will answer it directly.

    No. The platform is force-limited in hardware and carries capacitive skin on every proximal link, which is what allows it to work on a shared floor. What it does need is a risk assessment for each cell — our applications team produces that with you during stage three, and it is a document exercise rather than a construction one. Floors need no anchors, rails or reflective markers.

    Your own supervisors do, using teach mode. A typical pick-and-place or machine-tending task is demonstrated twice and refined once, which takes about 25 minutes end to end. Nothing is written in code. More complex sequences — multi-station kitting, for instance — are composed from library behaviours in the fleet console, and that is a drag-and-drop exercise rather than a programming one.

    It stops, holds position and escalates. Gen-3 will not improvise its way through an unrecognised scene: the task policy has a confidence envelope, and anything outside it raises an operator request in the fleet console with a frame of what it is looking at. An operator resolves it in seconds, and that resolution is available to every other unit on site.

    It is processed on board and, by default, stays there. Fleet telemetry — task outcomes, fault codes, battery health — is opt-in and configured by your administrator. Raw camera frames are never transmitted unless someone with administrator rights explicitly attaches them to a support ticket. The full account is in our Privacy Policy.

    Eleven line-replaceable modules, all accessible with a single hex driver. A forearm or lower-leg swap is a six-minute, two-bolt job that your maintenance team is trained on at commissioning. Consumables — pad sets, filters, the battery pack — have published service intervals, and spares ship from regional stock.

    Yes, in full, at any point up to the moment you counter-sign the site survey at stage three. After that the deposit is applied to the unit price and the standard cancellation terms in our Refund & Cancellation Policy take over. We do not hold a reservation you have asked to release.

    § 10 — Reserve

    Hold a build slot.

    Submitting this form places a non-binding reservation request. Nothing is charged here — an applications engineer confirms your slot and the deposit arrangement by email within two business days.

    Used only to confirm your reservation.
    1 to 250 per reservation.
    At least 20 characters. This goes straight to an applications engineer.

    No payment details are requested and nothing is charged at this stage.

    Reservation request received

    Your slot is provisionally held. An applications engineer will confirm the build position and deposit arrangement by email within two business days. Keep the reference below for any correspondence.

    REF · —